Analog Estimation Vs Parametric Estimation | Estimate Vs Budget | Contingency Reserve Vs Management Reserve

Analogous Estimation vs Parametric Estimation | Estimate vs Budget
...

Chandana

Published on May 24, 2012


  • 8323 Views

When the Project Manager is in the planning process group, most of his/her time will be used up in estimating resources, time  required to complete the project, the cost, risk planning, procurement planning, etc. The estimation can be done using different techniques like analogous, parametric, three point estimation, expert judgement etc. Let us first take up the difference between analogous estimation and parametric estimation.
 

Analogous Estimation vs. Parametric Estimation

Analogous Estimation

Analogous estimations are made based on the time or cost taken by similar older projects. Thus, these estimations are based on the experience of the team or the history of the project. The one disadvantage of this method is that the estimation may not always be accurate. 

For example, the developmental cost of an online booking application took about 1 month. You plan on developing a similar application. It can thus be assumed that the analogous estimation is 1 month. 

Parametric Estimation

Parametric estimation is done on a per unit basis and uses the relation between variables to arrive at the cost or the duration. Compared to the analogous estimation, parametric estimation stands to be more accurate. But the measurement must be scalable in order to achieve the accuracy.

For example, if it takes 1 day to produce 10 pieces of content, how mangy days will it take to produce 100 pieces of content? 
 

Estimate Vs Budget

We have differentiated between the two kinds of estimation. Now let us shift to estimate and budget. 

Estimate 

Estimation is the likelihood of the duration or the cost in terms of quantitative numbers to complete the project. But can we achieve the project with estimation? The answer is not really. So this ambiguity leads to adding a buffer called the estimate.

Estimate is an approximate figure to arrive at the duration, cost, effort, and resources to complete the project.

Budget 

Budget is approved estimate after the addition of reserve.

For example: After the estimation, if the cost is $1M, then it will add about 5% considering the reserve. So the budget will become $1.05M.
 

Contingency reserve vs Management reserve

We just talked about the reserve. 

PMP has two kinds of reserves - Contingency reserve and Management reserve. 

Contingency Reserve 
Contingency reserve is the amount of duration or the cost added based on the unknown but potentially identified risk. This will be added usually by the Project Manager after the estimation. 

Contingency Reserve is also called "known-unknown".

Management Reserve

Management Reserve is the amount of duration or the cost added based on the unknown risks that are not visible. This will be added by the Sponsor or the PMO office. For a project manager to use this reserve, it needs to be approved by the sponsor/PMO.

Management reserve is called “unknown”. The technique of using the Management Reserve and Contingency reserve is called the Reserve Analysis.

About the Author

Chandana is working as a Senior Content Writer in Simplilearn.com and handles variety of creative writing jobs. She has done M.A. in English Literature from Gauhati University. A PRINCE2 Foundation certified, she has a unique and refreshing style of writing which can engross the readers to devour each sentence of her write-ups.


{{detail.h1_tag}}

{{detail.display_name}}
... ...

{{author.author_name}}

{{detail.full_name}}

Published on {{detail.created_at| date}} {{detail.duration}}

  • {{detail.date}}
  • Views {{detail.downloads}}
  • {{detail.time}} {{detail.time_zone_code}}

Registrants:{{detail.downloads}}

Downloaded:{{detail.downloads}}

About the On-Demand Webinar

About the Webinar

Hosted By

...

{{author.author_name}}

{{author.author_name}}

{{author.about_author}}

About the E-book

View On-Demand Webinar

Register Now!

First Name*
Last Name*
Email*
Company*
Phone Number*

View On-Demand Webinar

Register Now!

Webinar Expired

Download the Ebook

Email
{{ queryPhoneCode }}
Phone Number {{ detail.getCourseAgree?'*':'(optional)'}}

Show full article video

About the Author

{{detail.author_biography}}

About the Author

{{author.about_author}}